The 180-day project will restore the arcades, historic flooring and public areas surrounding the casino and Gran Hotel Provincial
The restoration will address structural deterioration in one of Mar del Plata’s most recognisable tourism and gaming locations. It forms the second stage of a wider programme to renovate the city’s historic seafront complex.
The Government of Buenos Aires Province awarded the contract to a temporary consortium formed by CECOSA S.A. and PF Compañía Constructora S.A. The decision was formalised through Resolution No. 625 and corresponds to Public Tender No. 22/2026.
The construction contract is valued at ARS5.73bn. Once funding for project management, inspection, reserves and architectural enhancements is included, the total provincial investment rises to ARS6.02bn, equivalent to approximately US$4m.
The work must be completed within 180 consecutive days.
The project covers Plaza Bristol and the arcades of the Casino Central and Gran Hotel Provincial. It includes the semi-covered areas along the seafront façades and the sides of both buildings.
These areas currently show significant deterioration, particularly around the casino.
Structural work will include removing existing flooring, repairing and replacing the underlying surfaces and waterproofing the entire area to prevent leaks into the basements.
The project will also separate and renew the sewage and water installations serving commercial units facing the casino arcade. Public toilets beneath the Rambla will be renovated.
Restoration work will include the full replacement of historic flooring and the cleaning and repair of stone elements. Steps, ramps, stairways, columns and arches will also be restored where required.
The contractors will repair the woodwork, façades and entrances of commercial premises. New drainage, electrical and lighting systems are also included, together with the restoration of green areas and landscaping.
Four offers were submitted during the tender. The provincial evaluation committee selected the CECOSA and PF Compañía Constructora consortium after determining that its proposal was the most suitable for the public interest.
The remaining proposals from RIVA S.A.I.I.C.F.A., José Luis Triviño S.A. and Construcciones La Plata S.A. were rejected as less advantageous.
The wider Rambla programme covers 41,505 square metres and represents the first comprehensive restoration of the seafront complex since its inauguration in 1941.